1.0 Purpose : To provide a documented procedure for Procedure For Restart The Activities After Power Failure / Breakdown
2.0 Objective : Procedure For Restart The Activities After Power Failure / Breakdown
3.0 Scope : This SOP is applicable for. Restart The Activities After Power Failure / Breakdown at -----Pharmaceuticals Ltd,
4.0 Responsibility :
· Primary: Technician Engineering
· Secondary: Manager Engineering
5.0 Procedure :
· Power failure:
Ø Check the main power circuit panel for voltage and break down.
Ø Start the D.G. Set and check the voltage and frequency, it should be 430 V and 50 HZ
Ø Then changeover the power supply from G.E.B. to D.G. Set for normal operation.
Ø After resuming the power supply from G.E.B. check the voltage and frequency.
Ø Before changing over power supply from D.G. Set power supply inform the critical
Ø Processing areas personnel and switch. the power supply for normal working.
· BREAKDOWN :
Ø In case of breakdown of power supply, confirm the nature of breakdown.
Ø Start the D.G. Set
Ø Check the voltage and frequency; it should be 430 V & 50 HZ.
Ø Change over the power supply from G.E.B. to D.G. Set for normal working.
Ø After attending the breakdown of power supply, restore the power supply and check the voltage and frequency of mains.